Construction Projects

2017- 2018 Projects




US 2, Belknap Street Improvement Project
The Wisconsin Department of Transportation (WisDOT), in coordination with the City of Superior, is reconstructing US 2, Belknap Street, from Banks Avenue to Hill Avenue. 
This project replaces 1.4 miles of concrete roadway, upgrades the storm sewer system, and improves safety on Belknap Street. The project also includes improvements on most of the connecting side streets north and south of US 2, Belknap Street, back to the respective alleys. 
Phase I of the reconstruction of the street was completed in November  2017 and Phase II (the center section from John - Birch Avenue) will begin in the spring of 2018.  Please click on the link for information and updates from WisDOT.    More Information

Sidewalk Projects


 
Below are the areas where 2017 sidewalk work will be done.  If you are a homeowner in these areas, you will be receiving a letter further detailing the work and other important information about the project. 

Cumming Ave, 4th St to 5th St, east and west sides
Baxter Ave, 4th St to 5th St, east and west sides
Grand Ave, 4th St to 5th St, east and west sides
Weeks Ave, 4th St to 5th St, east and west sides
Clough Ave, 4th St to 5th St, east and west sides
Fisher Ave, 4th St to 5th St, east and west sides
N 6th St, Fisher Ave to Catlin Ave, north side
N 7th St, Baxter Ave to Grand Ave, north side
N 8th St, Clough Ave to Fisher Ave, north side
Fisher Ave, N 7th St to N 8th St, east side
Broadway St, John Ave to Hughitt Ave, south side
N 11th St, Hughitt Ave to Hammond Ave, north and south side
Hughitt Ave, N 11th St to N 12th St, east side
N 12th St, Hughitt Ave to Hammond Ave, north side
N 12th St, Baxter Ave to Grand Ave, north and south side
N 13th St, Hughitt Ave to Hammond Ave, south side
N 17th St, Hughitt Ave to Hammond Ave, north and south side

To view maps of the 2017 sidewalk projects, click here

If you live in these areas, please be mindful of "no parking" signs being put up on the streets as this is an indication that work will begin soon in your area and access will be needed for both the crews and their equipment.

Once work begins in your area, crews will be setting up forms, and pouring the new sidewalks.  Once poured, the concrete needs to cure and harden for one week.  During this curing process it is important that the concrete not be driven on or heavily used.  This is especially important if you have a sidewalk crossing your driveway access.

Your cooperation and patience with us as we work is very much appreciated.  If you have questions regarding this matter, please contact the Engineering Department at: 715-395-7300.



Milling & Paving List



Asphalt milling is anticipated to begin May 22, 2017 and Asphalt Paving Operations on about June 19, 2017.  Intended completion for this work is November 1, 2017.

Asphalt Overlay:
50th Ave E E 2nd St to St. Croix St. 
Billings Drive Windsor to N 21st 
Badger Drive Cul-de-sac to End
Huron Drive Cul-de-sac to End
Maryland Ave N 23rd St. to N 26th St. 
Iowa Ave N 23rd St. to Dead End
N 37th St. Tower Ave to the Frontage Road 
N 40th St. Tower Ave to the Frontage Road
John Ave N 10th St. to N 11th St. 
6th Ave E Laurel Ave to E 7th St. 
E 8th St 14th Ave E to N 21st St. 
13th Ave E E 8th St. to the Dead End
E 14th St. 24th Ave E to 23rd Ave E
Grand Ave N 24th St to 23rd Ave E
N 24th St. Grand Ave to Hill Ave
Raspberry E 9th St to Norwood Ave
Ogden Ave N 21 St. to N 28th St. 
Scharte Drive N 58th St to End

Mill & Asphalt Overlay:
N 5th St. Grand Ave to Catlin Ave
N 8th St. Grand Ave to Weeks Ave
N 8th St. Clough Ave to Catlin Ave
N 11th St. Catlin Ave to E Dead End 
Maple Ave Hill Ave to Raspberry Ave
Norwood Ave Hill Ave to Raspberry Ave
21st Ave E E 5th to E 8th 
N 17th St. Hammond Ave to Hughitt Ave
N 18th St. Hammond Ave to Hughitt Ave
N 22nd  St. Tower Ave to John Ave
N 23rd St. Tower Ave to John Ave
N 24th St. Ogden Ave to John Ave
Weeks Ave N 19th St to Faxon St. 
N 19th St. Catlin Ave to Weeks Ave
Weeks Ave N 19th St. to Faxon St. 

Alley Paving:
Between E 4th St. and E 5th St, 9th Ave E to 10th Ave E. 
Between Lincoln and N 20th St, Weeks Ave to Clough Ave. 
Between E 3rd St and E 4th St, 53rd Ave E to 54th Ave E. 
Between Hammond Ave and Cumming Ave, N 18th St to N 19th St. 
Between Tower Ave and Banks Ave, N 18th St to N 19th St



2018 Alley Paving



If your alley is scheduled to be paved in 2018, the petitions, maps and the costs to homeowners can be found by clicking on the alley below.  If you would like information about our alley paving program, please click on the "Street Division" tab on the left and you can read the policy and get a copy of the petition.

1. 13th & 14th Avenues East; between East 7th & East 8th Streets 

2. North 14th & Belknap Streets; between Cedar & Hill Avenues

3. North 21st & North 22nd Streets; between Tower & Ogden Avenues (T-alley)

4.  19th & 20th Avenues East; between East 6th & 7th Streets

5. Cedar & Hill Avenues; half block north of North 14th Street

6. North 18th & 19th Streets; between Missouri & Maryland Avenues